The objective of the technical design was to develop a shoring solution for a deep excavation intended for the installation of a single-component tank. For this project, an OWS-series shoring system was utilized, integrated with a top waling beam (capping beam). This configuration created a strut-free (clear-span) excavation, which allowed for the smooth and rapid installation of the tank in a single stage.
Deep Excavation Dimensions:
- Length: 12,00 m
- Width: 4,00 m
- Working depth: 4,20 m
KOPRAS was responsible for the detailed design of the temporary deep excavation shoring, as well as the preparation of the Technical Specifications for the Execution and Acceptance of Construction Works.